Brazil’s state-owned energy research firm EPE unveiled on Tuesday that 29,411 MW of renewable energy projects have been registered for the next auction that will be held on August 31, 2018.
In addition to renewable sources, the tender will contract power from thermal plants that use natural gas and coal. Overall, 1,080 energy projects totalling 57,959 MW will compete for contracts.
More details by capacity are available in the table.
Projects Qualified to the August 31 New Energy Auction
PROJECT TYPE | PROJECTS QUALIFIED | FIRM CAPACITY |
---|---|---|
Wind Power Plant | 926 | 27,058 MW |
Hydro Power Plant | 7 | 333 MW |
Small Hydro Power Plant | 63 | 919 MW |
Cogeneration | 21 | 61 MW |
Biomass | 25 | 1,040 MW |
Coal-fired Thermal Plant | 2 | 940 MW |
LNG Thermal Plant | 36 | 27,608 |
In Brazil, hydropower plants (HPP) are divided into three groups depending on their capacity. UHE, with capacity exceeding 30 MW, PCH, between 1 MW and 30 MW, and CGH of up to 1 MW.
This energy tender will award 20-year supply contracts for wind power, 30-year deals for hydropower, and 25-year contracts for other sources. The power plants should commence operations on January 1, 2024, EPE noted.